Overview
RESIDENTIAL PERMITS | Fee |
---|---|
Connection | |
New Job – new gas installation (includes 3 appliances) | $195.00 |
Each additional appliance | $65.00 |
Re-connection of gas installation that has been out of service for over 1 year | $65.00 |
Underground – piping or tubing installed underground | $65.00 |
Improvement | |
Addition – when a gas appliance or outdoor outlet is added to existing gas installation | $65.00 |
Replacement of gas appliance or heat exchanger | $65.00 |
Alteration of gas installation piping and/or venting (not covered under another gas permit) | $65.00 |
Temporary (90 Days) | |
Each appliance | $65.00 |
Propane tank set | |
Each Propane Tank Set (not required when included in New Job permit) | $35.00 |
COMMERCIAL PERMITS | Fee |
Connection | |
New Job – new gas installation (includes 1 appliance) | $325.00 |
Each additional appliance | $180.00 |
New Food truck | $325.00 |
Re-connection of gas installation that has been out of service for over 1 year | $180.00 |
Underground piping or tubing | $180.00 |
Total Load excess of 1 million btu/hr (each million btu/hr or portion thereof in excess of 1 million btu/hr) | $100.00 |
Improvement | |
Addition – when a gas appliance is added to existing gas installation | $180.00 |
Replacement of gas appliance or heat exchanger | $180.00 |
Alteration of gas installation piping and/or venting (not covered under another gas permit) | $180.00 |
Total Load excess of 1 million btu/hr (each million btu/hr or portion thereof in excess of 1 million btu/hr) | $100.00 |
Temporary – 90 Days | |
First appliance | $125.00 |
Each additional appliance | $55.00 |
Mobile trailer (tank set permit included) | $75.00 |
Each exhibition/trade show concession (tank set permit included) | $75.00 |
Propane Tank Set | |
Propane Tank Set 120 – 5,000 USWG | $35.00 |
Propane Tank Set > 5,000 USWG | $750.00 |
Propane refill centers, propane storage and filling plants (separate application with site plan required) Up to and including 5,000 USWG | $250.00 |
Propane refill centers, propane storage and filling plants (separate application with site plan required) Over 5,000 USWG | $750.00 |
Other | |
Grain Dryer > 400,000 btu/hr | $325.00 |
Bin Dryer up to 400,000 btu/hr | $65.00 |
Turbines | $5,000.00 |
Micro-turbine, gas engine, fuel cell < 1 million btu/hr | $325.00 |
Bunsen burners in lab room(s) – Per Room | $180.00 |
Each natural gas vehicle refueling facility with storage | $750.00 |
Total Load excess of 1 million btu/hr (each million btu/hr or portion thereof in excess of 1 million btu/hr) | $100.00 |
Oilfield | |
Well Head (includes 2 pieces of equipment: tank heater, gas engine, &/or catalytic heater) | $325.00 |
Each additional or replacement tank heater or gas engine | $180.00 |
Each additional or replacement catalytic heater | $75.00 |
Field Approvals | Fee |
Multiple (Single wellhead tank burner, or Combustor pilot, rated under 1 million btu/hr) | $350.00 |
400,000 and less btu/hr burner, or combination of burners, operating independently | $1,000.00 |
Over 400,000 up to 5 million btu/hr | $1,250.00 |
Over 5 million less than 12.5 million btu/hr | $2,500.00 |
12.5 million btu/hr and greater | $3,000.00 |
Each 20 million btu/hr, or portion thereof, in excess of 50 million btu/hr | $500.00 |
Inspection/Professional Services (Hourly Rate) | Fee |
Return Inspections performed upon installations whose previous inspection resulted in the identification of corrective actions (reinspection/follow-up) | $155.00 |
Unreported gas installations | Up to $2,500.00 |
Additional Inspection/Professional Services:
|
$155.00 |
Retail Propane Exchange Site (separate application with site plan required) | $250.00 |
Plans Review (Hourly Rate) | Fee |
For gas systems exceeding 5 million btu/hr load or lines exceeding 2000 ft. length | $155.00 |
Premium Rates for Inspections beyond Regular Working Hours | Fee |
Special Inspection Services (inspections performed during regular overtime working hours or when inspection services are requested without providing 24 hours prior notice) | $232.50 |
Special Inspection Services Performed on Public Holidays (Statutory) | $310.00 |
Travel Related Expenses | Fee |
Rate for Vehicle Travel – per kilometer | $0.69 |
Rate for Meals – per meal | $20.00 |
Rate for Accommodation, Incidentals (including parking), and Flights | Actual Cost |
Licence (1 Year) | Fee |
Gas Fitter (General, Domestic or Restricted) | $40.00 |
Gas Contractor (General, Domestic or Restricted) | $225.00 |
Gas Employer | $225.00 |
Gas Supply House | $225.00 |
Propane Distributor | $150.00 |
Propane Distributor (General or Domestic) | $150.00 |
Propane Retailer | $50.00 |
Propane Wholesaler | $50.00 |
Licence (3 Years) | Fee |
Gas Fitter (General, Domestic or Restricted) | $100.00 |
Gas Contractor (General, Domestic or Restricted) | $575.00 |
Gas Employer | $575.00 |
Gas Supply House | $575.00 |
Propane Distributor | $450.00 |
Propane Distributor (General or Domestic) | $450.00 |
Propane Retailer | $125.00 |
Propane Wholesaler | $125.00 |
Examination | Fee |
Restricted Gas Fitter | $57.00 |
Administrative Services | Fee |
Hourly Administrative Rate | $63.00 |
Gas Verification Tags | $8.00 |
Application for appeals against the inspector | $200.00 |
Application for variance from code requirements | $100.00 |
Hourly Rate for appeals and variance from code requirements | $200.00 |
Interest charge on overdue accounts | 18% per annum (1.5% monthly) |
NSF Cheques | $37.00 |
Terms & Conditions | |
|
|
Unless otherwise specified within this schedule, rates per hour are based upon ½ hour or portion thereof – minimum 1 hour. | |
All fees subject to GST where applicable |